logo
Before the Next Flood: NYC Needs More Progress Building Green Infrastructure

Data - November 2021

Before the Next Flood: NYC Needs More Progress Building Green Infrastructure

While the city has made significant progress in ramping up the construction of green infrastructure, it has fallen short of state-mandated targets and struggled to finish construction on thousands of green infrastructure assets in a timely manner. The next administration needs to expand its goals and accelerate construction throughout the city.

by Laird Gallagher

Tags: infrastructure resilience sustainability boroughs

The devastating flooding caused by Hurricane Ida has brought renewed focus on the importance of building green infrastructure, which experts believe is critical to lessening the impact of rainstorms on the city's aging sewer system. New research by the Center for an Urban Future finds that while the de Blasio administration has made significant progress in constructing green infrastructure, it has still not met the city’s goals for 2015, has completed only a fifth of the green infrastructure projects started in post-2015 contingency plan areas, and has barely built any green infrastructure assets in the Bronx, Staten Island, and Manhattan.

The city is still yet to verify its first milestone – the 2015 goal for green infrastructure to reduce combined sewer overflows by just 2.4 percent of the citywide baseline, or 507 million gallons per year.1 After missing that first five-year target laid out in the city’s 2010 Green Infrastructure Plan—due in part to Hurricane Sandy—the de Blasio administration developed a Contingency Plan in early 2016, designed to reach its 2015 target by 2020. The administration has been aggressive in trying to catch up; when complete, the projects it launched beginning in 2016 will nearly triple the amount of green infrastructure assets throughout the city. But our research shows that even this important push is mostly still a work in progress: just 21 percent of the 7,346 new assets launched after 2016 have been completed; 79 percent remain under construction.2

Mayor-elect Adams will need to do a lot more. With climate change leading to more frequent and severe rainstorms that overwhelm New York’s century-old sewer system, the city must expand its goals for green infrastructure development and increase the pace at which construction occurs.

The Adams administration will also need to address geographic gaps in green infrastructure. Our research shows that while some city neighborhoods have seen concentrated rollouts of curbside rain gardens and other green infrastructure, most of the city has been neglected. 55 percent of fully constructed green infrastructure (2,976 assets) are in Queens and 36 percent (1,972) are in Brooklyn. Less than 7 percent (364 assets) are in the Bronx, while less than 2 percent (82 assets) are in Manhattan. (In all of Manhattan, the only green infrastructure assets currently under construction are three grant-funded rain gardens in Two Bridges.)

Progress on Green Infrastructure (September 2021)

BoroughConstructedFinal DesignIn ConstructionTotal
Bronx36416547927
Brooklyn1,9721,8381,7945,604
Manhattan827392
Queens2,9766673,4557,098
Staten Island120012
NYC5,4062,5285,79913,733

 

 

Strikingly, just 12 green infrastructure assets are located on Staten Island out of 5,406 built assets throughout the city. There is no additional green infrastructure in final design stages or under construction on Staten Island.

With Hurricane Ida revealing that neighborhoods all over the city are at risk of flooding from increasingly powerful storms, significantly more progress is needed in all boroughs.

The Big Picture

This data brief examines New York City’s progress on constructing new green infrastructure—including curbside rain gardens; green roofs; and permeable surfaces on paths, roads, and play surfaces at parks, schools, NYCHA campuses, and other city-owned property throughout the city. The construction of green infrastructure assets has the potential to capture and divert billions of gallons of stormwater runoff away from the city’s century-old sewer system, where just one-tenth of an inch of rainfall can cause “Combined Sewer Overflows” (CSOs)—the discharge of stormwater mixed with untreated sewage directly into local waterways.3

Lessening the burden of rainfall on the city’s combined sewers is critical in normal times because nearly every time it rains the system becomes overwhelmed, ultimately discharging over 20 billion gallons of raw sewage mixed with stormwater into New York City’s waterways every year.4 Now, with climate change causing more frequent and severe rainstorms, green infrastructure must play an increasing role in mitigating flooding, too.

The city’s green infrastructure plan is a key component of how the city plans to reduce CSOs, as required by a Consent Order between NYC DEP and the New York State Department of Environmental Conservation (DEC). But as heavy rainstorms increase in frequency, at minimum, the city’s rollout of green infrastructure should keep pace, and our research confirms that NYC DEP is falling behind state-mandated targets.

Key findings of our data brief include:

  • From 2016 to September 2021, the total number of green infrastructure assets built or in construction increased by 190 percent, from 3,859 assets in 2016 to 11,205 assets today.
  • But just 21 percent of green infrastructure (1,547 assets) that has gone into construction since 2016 is fully built. Fully 79 percent (5,799 assets) is under construction. An additional 2,528 are in final design stages.
  • 60 percent of green infrastructure assets under construction (3,455 assets) are in Queens and 31 percent (1,794) are in Brooklyn. Just 9 percent (547) are in the Bronx. Only 3 assets are under construction in Manhattan, and none in Staten Island.
  • 73 percent of green infrastructure assets in the final stages of design (1838 assets) will be located in Brooklyn, and 26 percent (667) will be located in Queens. Roughly 1 percent of green infrastructure in final design will be sited in the Bronx (16 assets), Manhattan (7), or Staten Island (0).
  • Only 22 percent (1688 assets) of green infrastructure included in Contingency Plan projects has been constructed as of September 2021. 72 percent (5,411 assets) is in construction, and 6 percent (420 assets) is in final design.

The Way Forward

There are over 78,000 acres of impervious area in the parts of New York City that use the combined sewer system. The goal of NYC’s 2010 Green Infrastructure Plan was to use green infrastructure to capture the first inch of rainfall on 10 percent of that area by 2030, reducing combined sewer overflows by a total of 1.67 billion gallons per year. But the city has already missed the first two five-year milestones: 1.5 percent by 2015, and 4 percent by 2020.

For New York to not only meet the state-ordered 1.67-billion-gallon CSO reduction within the next 9 years, but also take steps to mitigate increased flooding due to climate change, the city will have to redouble its efforts and deploy green infrastructure in every neighborhood throughout New York City.

Scale up the original Green Infrastructure Plan, set new goals, and develop a strategy to get there more quickly. The city’s first Green Infrastructure Plan was established by the Bloomberg Administration in 2010, long before Hurricane Sandy and Hurricane Ida. As storms become more frequent and severe due to climate change, the city must reevaluate its approach. The city should make green infrastructure a central part of mitigating flooding and keeping New Yorkers safe. It should set new goals to reduce sewer overflows by billions more gallons per year and develop a plan to meet those goals on time.

Prioritize fixing the capital construction process for green infrastructure. Just 21 percent of the green infrastructure assets that have gone into construction since 2016 are fully built. The city cannot afford to take several years to build rain gardens and bioswales if it is to meet its fast-approaching 2030 goal. The next mayor should build on DDC capital reforms and push all agencies involved in building green infrastructure—from DEP and DOT to EDC, OMB, DOE, and the Parks Department—to follow through with the bold reforms needed to reduce project delays. Nearly all the recommendations in our Stretching New York City’s Capital Dollars report apply equally to green infrastructure.

Greatly expand and accelerate the rollout of Right-of-Way (ROW) green infrastructure in all five boroughs. Though public roads and sidewalks make up 30 percent of the city’s impervious area, the vast majority of the city’s roadways—including nearly all of Manhattan and Staten Island—have no rain gardens, catch basins, or permeable surfaces to capture stormwater. The city should accelerate plans for area-wide green infrastructure contracts beyond the priority neighborhoods in Brooklyn and Queens that have been the focus for the past decade, with new attention to areas with combined sewers but little to no planned green infrastructure, such as Manhattan, Southwest Brooklyn, and the South Bronx.

Fast-track Cloudburst Projects Hurricane Ida and other devastating rainstorms this year show the city must act now to manage stormwater from extreme rain events, also known as “cloudbursts,” which are increasing in frequency and severity due to climate change. DEP should explore all options for managing flash flooding, including using streets, parks, and other public spaces. The city should prioritize cloudburst projects in the areas most affected by Hurricane Ida and move quickly beyond feasibility studies to begin the rollout of neighborhood-scale solutions to divert floodwaters and keep communities safe.

Green Infrastructure assets across NYC that are built (green), under construction (yellow), or in final design (blue).

Contingency Plan Projects for the 2015 Milestone – Status as of 9/1/2021

Project NameConstructedFinal DesignIn ConstructionTotal
DDC BB Cluster (BB-009)15200152
DDC BB Cluster (BB-013)2002
DDC BB Cluster (BB-026)13300133
DDC JAM-003 Phase 117700177
DDC JAM-003 Phase 261102613
DDC JAM-003 Phase 32250390615
DDC NCB-014700410480
DDC TI-010 Phase 1490499548
DDC TI-010 Phase 200396396
DDC TI-010 Phase 300301301
DDC TI-010 Phase 400657657
DDC TI-01121900219
EDC 26W-00400176176
EDC 26W-005 Phase 100625625
EDC 26W-005 Phase 200776776
EDC 26W-005 Phase 300371371
EDC HP-002130013
EDC HP-004370037
EDC HP-007 Phase 100112112
EDC HP-007 Phase 200211211
EDC HP-014 Phase 1001818
EDC HP-014 Phase 2004848
EDC HP-014 Phase 3005959
EDC HP-033006767
OGI BB-005 (GI-DCM-TOC) Phase 1084084
OGI BB-005 (GI-DCM-TOC) Phase 201320132
OGI BB-005 (GI-DCM-TOC) Phase 300175175
OGI BB-005 (GI-DCM-TOC) Phase 400118118
OGI BB-005 (GI-DCM-TOC) Phase 502040204
Total168842054117519

 

Notes

1. NYC DEP, Green Infrastructure Performance Metrics Report, June 2016. https://www1.nyc.gov/assets/dep/downloads/pdf/water/stormwater/green-infrastructure/gi-performance-metrics-report-2016.pdf
Larry Levine, “NYC’s New Plan Would Let Massive Sewage Overflows Continue,” NRDC, February 24, 2020. https://www.nrdc.org/experts/larry-levine/nycs-new-plan-would-let-massive-sewage-overflows-continue

2. NYC DEP, Green Infrastructure Performance Metrics Report, June 2016. https://www1.nyc.gov/assets/dep/downloads/pdf/water/stormwater/green-infrastructure/gi-performance-metrics-report-2016.pdf

3. NYC DEP, Green Infrastructure Contingency Plan for the 4% Implementation Rate Milestone, June 30, 2021. https://www1.nyc.gov/assets/dep/downloads/pdf/water/stormwater/green-infrastructure/gi-contingency-plan-2020.pdf

4. CUF analysis of NYC Green Infrastructure 2017 Annual Report https://www1.nyc.gov/assets/dep/downloads/pdf/water/stormwater/green-infrastructure/gi-annual-report-2017.pdf CUF analysis of DEP Green Infrastructure data, September 2021. https://data.cityofnewyork.us/Environment/DEP-Green-Infrastructure/spjh-pz7h

This report was made possible thanks to support from the Lily Auchincloss Foundation for ongoing research on the intersection of sustainability and New York’s economy. General operating support for the Center for an Urban Future has been provided by The Clark Foundation, the Bernard F. and Alva B. Gimbel Foundation, and the Altman Foundation.